Corpach Marina - Community project
This project valued at around £3.3m started on site in June 2020. Our client is a community regeneration company. The works included marine and civil engineering works to construct a new car park and slipway, building works to provide a new marina facility including café and visitor centre, and the installation of breakwaters and pontoons to provide 45 berths.
It all starts with an idea
We have advised the client throughout on matters such as planning, building warrant, procurement, and construction management, and have been responsible for securing planning permission, marine licences, utilities connections and various other consents and approvals.
The works are within an area designated as a Scheduled Monument and adjacent to Listed Buildings and are in an area of high flood risk, all challenges which we have overcome. There were various restrictions on grant funding and deadlines to submit claims, all of which have been achieved, and we worked hard to mitigate the impact of the Covid-19 pandemic. The project remained on track within the original budget.
Project
Thomas Telford Corpach Marina
Year Complete
August 2023
Client
Caol Regeneration Company
Year Start
January 2018
Scope of Works
Northern Light work closely with the TTCM board; our scope of work included:
Raising grant funding to build the project
Engaging with stakeholders and securing support
Outline design of the civil engineering and building works – originally including the refurbishment of historic buildings but later changed to a new build structure
Managing the design process
Drafting tender documents for three separate contracts and managing the procurement in line with public sector procedures
Contract administration
Supervision of the works on site
Reporting progress and costs
Preparing grant claims